ECEARTH3 perfs¶
Action item : Performance analysis of the high-resolution configuration of the EC-EARTH 3Partner(s) : SNIC-LiU, SARA, ...,
PM available (SNIC-LiU) : 3 from 7.2 + 1.2 from 7.5 + 4 from IS-ENES = 8.2 pm
Time spent : 1.5 pm
Timeline :
- Initial testing of high resolution ec-earth on local cluster – end Feb 11
- Initial scaling report – mid April 11
- Initial testing on Curie system – end May 11
- porting of the code – end July 11
- scaling studies – end Sept 11
- scaling bottleneck analysis – end Dec 11
- tuning – end March 12
- report – end May 12.
- Done scaling studies of high resolution EC-EARTH on a local cluster
- Looking into different profiling / performance analysis tools for scaling bottleneck analysis.
- Will see impacts of different MPIs, compilers, optimization flags.
- Some tuning is done, waiting for access to Curie
- Porting on Curie
- Scaling test and tuning on Curie
- The initial report on high resolution ECEARTH3 scaling: ec-earth
- Scaling results on Curie presentation for meeting 11/12/07: ec-earth
- Scaling results on Curie presentation for meeting 11/12/07: ec-earth
- Scaling, OpenMP, I/O results of EC-EARTH@T159-ORCA1 for meeting 7 dec 2011